Copyright © 2010 OKD, a.s.
OKD, a.s.
POP 2010
OKD is the only producer of hard coal (bituminous coal) in the Czech Republic. Its coal is mined in the southern part of the Upper-Silesian coal basin – in the Ostrava-Karviná district... more »

If cooperation works fine, it is possible to achieve a lot of things

24.10.2008

KARVINÁ MINE – 105 thousand tons of coal with a total advancement of 150 metres! The sixth best result in the monthly mining and the eighth best one in the advancement, experienced in the Karviná Mine, ČSA Mining Plant over the last ten years! That’s a September achievement  of Alpex contractor’s team, consisting of 120 workers and headed by Ireneusz Czarniakowski, Head of the Field and Stefan Gulak, Chief Foreman.

 

“It is a super team, one of the best ones in the ČSA Mining Plant for a long time,“ Petr Škorpík, Production Manager of the Karviná Mine appreciates Polish miners’ work. However, he immediately adds that this time, the team was strengthened by one crew of Tadeusz Swed’s working party, headed by Rostislav Kolář, Foreman. “It was done so as to ensure a really continuous operation, including Saturdays and Sundays,“ he explains.

 

The extraordinary result was born in a field of the Doubrava pillar, in Coalface 22 3452/1. The mining  at a length of 160 metres and thickness of 3.1 metres was carried out by means of Cutting-Loading Machine KGS 440 RW, Mechanical Support FAZOS 15/31 MOD and other equipment. The average daily advancement for 30 working days was 5 metres and the daily mining output amounted to 3,500 tons. The working party also complied with the limit mining output parameters, and after the excellent result from the end of the last year, they have recorded another achievement.

 

“The result is even more precious in the light of the fact that it is the remotest work area in the whole mine,“ Petr Škorpík emphasizes the fact that the success has not come just so. “The distance from the mine shaft is approximately four kilometres. The guys must go on a rail and suspension locomotive and must walk the rest of the distance. It takes them approximately one hour. If they, i.e. both the Polish and Czech miners, had not worked on extended shifts, they would have never accomplished such an objective.“

 

“If the work goes well, it is of course super. At last, we got a coalface which offered solid conditions, and the guys have managed to take advantage of that,“ Ireneusz Czarniakowski, Head of the Coal Field specifies his view. “What we are building on is qualified and experienced personnel. Key is the cooperation with the maintenance & service personnel, i.e. mechanists, central mucking workers, central maintenance personnel, conveyance personnel and others. Without their efforts, it would not have been possible to accomplish any such objective. At present, the guys from  Tadeusz Szwed’s working party have helped us. And if all stick together, a lot of things can be achieved.“


In the Karviná Mine, ČSA Mining Plant, all working parties of Alpex contractor, who unambiguously lead the production, are currently successful. They mine three out of nine active coalfaces and deliver approximately 60 per cent of the total mining output.

 

(Bohuslav Krzyžanek)


Company profile

OKD (PDF)
We support

Nadace OKD Občanské sdružení svatá Barbora Hornické muzeum OKD
Hard coal story Hard coal story
Events
« »
May 2012
Mo Tu We Th Fr Sa Su
30 1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31 1 2 3
We are part of the group New World Resources
Articles TOP Philanthropist 2010: OKD – Second Most Generous Donor
i-region.eu

Prague/Ostrava (12 November 2010) – OKD, the mining company, was ranked second in the prestigious ...

more
CZ EN PL
Do you know that...
OKD is the only producer of hard coal in the Czech Republic; Its coal is mined in the southern part of the Upper-Silesian coal basin. more »
Do not miss NWR Open Mine Magazine No. 1/2012
The Company Magazine...here

NWR Open Mine Magazine No. 4/2011
The Company Magazine...here

Announcement of suspected fraud

OKD, a.s., has been currently exposed to fraudulent activity by unknown individuals in Germany.
Full version of the document in English and German is here.


BUSINESS INTEGRITY POLICY

This policy was adopted by the Board of Directors of New World Resources Plc on 15 November 2011 and shall have immediate effect.
Full version of the document is here.


NWR Open Mine Magazine No. 3/2011
The Company Magazine...here

NWR Open Mine Magazine No. 2/2011
The Company Magazine...here

NWR Open Mine Magazine No. 1/2011
The Company Magazine... more

Company code of ethics

The Board of Directors of OKD has adopted a Company code of ethics that is obligatory for all the employees of the firm. It defines basic values and attitudes to enterprise that OKD conforms to in the course of its business activities.

The code of ethics is not any binding rule of law or internal directive, it represents, however, a moral obligation for each employee of OKD.

Full version of the code


That's what we do... Take a look
Copyright © 2010 OKD, a.s.

OKD, a.s. seated Ostrava, Moravská Ostrava, Prokešovo náměstí 6/2020, Postcode  728 30,
incorporated in the Commercial Register kept by the Regional Court  in Ostrava, Section B, Inset  2900,
Identification Number: 26863154, Taxpayer Registration Number: CZ26863154.